Employer / Administration
DSI 7th Regional Directorate
Samsun District Bridge and Culvert Construction 2th Section
Construction of vehicle bridges 23 prefabricated beam and 2 steel beam, creek rehabilitation an refortify in Samsun province districts
310.000,00 m³ excavation of all types of ground, 18.607,00 m³ stone filling, 27.550,00 m³ concrete puring, 4.651,00 tons of reinforcement Works, 986 tons of beam manufacturing, replacement and painting, Ø100 cm 6.458 m cast piles, Ø120 cm 3.619 m cast piles, construction of 3.386 m³ prefabricated beams for bridges, supply and installation of 208 tons of precast steel